Search

Premium Membership ♕

Limited Time Offer: Save 10% on Pro Plan with coupon: 110VDC. Study specialized LV/MV/HV technical articles & studies.

Home / Technical Articles / Checks for Successful Substation Factory Acceptance Testing

Prefabricated Substation FAT

This technical article will go over various aspects of factory acceptance testing (FAT) for custom prefabricated power substation and its related electrical components (such as MV and LV switchgear, MV-LV Motor Control Centre (MCC), UPS systems, AC/DC auxuliary power supply panels, and so on) to ensure that the systems were properly manufactured in full compliance with design specifications.

Checks for Successful Substation Factory Acceptance Testing
Checks for Successful Substation Factory Acceptance Testing

We will look at the different stages of the project life cycle to address the protocols and safety measures necessary for a successful factory acceptance test (FAT).

The testing aims to verify that the equipment and systems function properly and comply with the manufacturers’ specifications and relevant standards. This work entails multiple risks. The user bears the responsibility for safety. An examination of regulatory constraints is necessary before conducting tests.

It’s worth mentioning that there are no standard FAT or SAT work instruction documents. Both testers and commissioners have variations of their testing and commissioning documents.

To summarize, Factory Acceptance Testing  are conducted to ensure compliance with specific specifications, resulting in high-quality products. The tests are typically conducted with the customer and, in more rigorous circumstances, with a third-party inspection agency.

While all switchgear is expected to be faultless upon delivery from the subcontractors responsible for their assembly, defects occasionally arise. Consequently, these manufacturing acceptance tests are essential. During a FAT, installations are meticulously verified to ensure they conform to the project-specific drawings. Functions intended to operate upon switchgear installation at the site are also simulated to verify automated capability.

All potential problems, deviations, and requests are duly recorded.

This technical article will underscore the significance of a comprehensive and organized Factory Acceptance Test (FAT) for a successful substation startup and operation.

Table of Contents:

  1. Prefabricated Power Substation:
    1. What is a Prefabricated Power Substation?
    2. Equipment Inside the Substation Building
  2. FAT Agenda:
    1. DAY #1
      1. Bid Clarification
      2. Kick Off Meeting
      3. Safety Precautions During Electrical Inspection
      4. Equipment Internal Inspection
    2. DAY #2
      1. Bid Clarification
      2. Pre-FAT Meeting
      3. FAT Process (Test-Punch list-Retest)
  3. Bid Clarification Process
  4. Kick Off Meeting:
    1. Project Clarification
    2. Define Project Members and Their Roles
    3. Project Organization Chart
    4. Technical Specification
    5. Review QA/QC Procedures & Forms
    6. Capture Meeting Minutes
  5. Safety Precautions During Electrical Inspection:
    1. PPE for Electrical Inspection
    2. General Safety Precautions and Checks
    3. Special Precautions
    4. Customer Inspection Safety
    5. Conclusion
  6. Equipment Internal Inspection:
    1. Process Flow Chart
    2. Equipment Line History Checklist
    3. Useful Checks
    4. Review Meeting Minutes
  7. Final Inspection and Equipment Testing:
    1. Visual Inspection
    2. Bussing Check
    3. Mechanical Tests
    4. CT Inspection
    5. Control Tests
    6. Primary Injection Test
    7. High Potential Test (HIPOT)
    8. High Voltage Test
    9. Substation Automation Testing:
      1. IED Configuration and Management
      2. Verify Communication Architecture
      3. Verify ECMS
  8. Other Substation Equipment Tests:
    1. UPS System Tests
    2. AC & DC Circuit Breaker Panel Tests
    3. Battery Chargers
    4. Annunciators
  9. Attachment (PDF) 🔗 Download ‘Analysis Handbook for Power Systems Using MATLAB and ETAP’

1. Prefabricated Electrical Substation

1.1 What is a Prefabricated Power Substation?

A prefabricated power substation is a substation that has been specially engineered, prefabricated, and completely integrated to satisfy the exact requirements of the electrical system package while reducing expediting and on-site civil construction costs. And that’s it, as simple as that.

It primarily comprises transformers, associated switchgear, and control panels, all contained within a protective enclosure. It can facilitate secure and effective electricity delivery.

In contrast to traditional substations, prefabricated substations do not necessitate the construction of onsite structures. These substations are delivered as integrated systems, significantly reducing installation time and labor hours required for setup.

Manufactured in a controlled environment, these prefabricated substations are constructed in compliance with standards and safety rules.


1.2 Equipment Inside the Substation Building

  • Low-voltage and Medium-voltage Switchgear,
  • Motor Control Centers (MCC),
  • Oher Associated Electrical & Control Equipment (i.e. VFD, UPS, Batteries, Instrumentation, etc.)
  • HVACs
  • Equipment for Fire & Gas Detection / Suppression
  • MV/LV Switchgear
  • MV/LV MCC
  • UPS Systems
  • Battery Chargers
  • SS automation

Figure 1 – Package & Containerised Substation

Package & Containerised Substation
Figure 1 – Package & Containerised Substation

Go back to Content Table ↑


2. FAT Agenda

DAY #1

1. Bid Clarification

  1. Review Request for Quote (RFQ) package and all commercial/technical documents
  2. Initiate estimating process & provide quote for the project

2. Kick Off Meeting

  1. Define project members and their roles.
  2. Project clarification and review documentation.

3. Safety Precautions During Electrical Inspection

  1. General precautions/checks that needs to be observed/made before & during testing of electrical equipment.
  2. Understanding the manufacturing facility & equipment under test.

4. Equipment Internal Inspection

  1. Getting equipment ready for the inspection.
  2. Check equipment against all checklist and start with in-process inspection.
  3. Start final inspection by performing various tests on the equipment (such as bussing check, control check, primary injection test etc.)
  4. Make sure equipment is ready for the factory acceptance test.

Figure 2 – Visual inspection check of a medium voltage switchgear

Visual inspection check of a medium voltage switchgear
Figure 2 – Visual inspection check of a medium voltage switchgear (photo credit: Colombara Romeo)

Go back to Content Table ↑


DAY #2

1. Bid Clarification

  1. Define project scope, schedule and timeframe for each phase of project.

2. Pre-FAT Meeting

  1. Review inspection test plan (ITP) for each equipment type.
  2. Define roles of each team member who is going to perform/witness the test.
  3. Set an agenda illustrating the FAT schedule.

3. FAT Process (Test-Punch list-Retest)

  1. Functional Check of:
    • MV/LV MCC
    • MV/LV Switchgear
    • Annunciators
    • Fire Alarms
    • HVAC
  2. Plant interlock scheme
  3. Temporary power panel
  4. Ship prep after FAT

Watch Lesson – Insights into Commissioning & Troubleshooting

Go back to Content Table ↑


3. Bid Clarification Process

The bid clarification process begins when a project issues a Request for Quotation (RFQ) which includes technical and commercial requirements.

  • The technical information includes the details specifying the equipment details and fabrication specifications.
  • The Sales Engineer/Estimating Engineer performs a detailed review of the project specifications/drawings and creates a costed bill of material and preliminary layout, which meets the requirements of the RFQ.
  • Any exceptions to the technical specifications are identified and documented by the person estimating the job.

The preliminary design includes:

  • Outline dimensional information for Pre-fab building/Equipment sizing.
  • Estimated material & labor costs based on project’s spec interpretation.
  • Preliminary Bills of Material (BOM’s) including Pre-fab building, buyout items, Switchgear, MCC’s, Bus Duct, breakers and devices as per the project specifications.
Once quote proposal is submitted the process of bid evaluation & negotiations starts. After successful bidding, purchase order or Letter of Intent (LOI) will be issued.

Go back to Content Table ↑


4. Kick Off Meeting

Kick-off meetings are invaluable to disseminating information within the project environment. It is extremely important that correct and accurate information is processed and transferred from project to engineers.

This is the opportunity for vendor to ensure that their interpretations are per project requirement and also an opportunity for customer to understand what they are really getting from the vendor.

Figure 3 – Kick Off Meeting Example

Kick Off Meeting
Figure 3 – Kick Off Meeting

Go back to Content Table ↑


4.1 Project Clarification

  1. Ensure that all technical discrepancies and questions have been addressed prior to starting the design process.
  2. Lesson learned from the past projects.
  3. Discuss any unique fabricated or buyout items, alignment of vendor deviations or exceptions from the project requirements, or any long lead time items.

Go back to Content Table ↑


4.2 Define Project Members and Their Roles

  1. Review project organization chart and associated roles.
  2. Discuss the tasks of different vendors associated with the project and the associated deliverables expected to be produced.

Each project participant should know their responsibility and understand the issues that may impact the successful completion of the project.

Go back to Content Table ↑


4.3 Project Organization Chart

Figure 4 – Substation FAT organization chart

Substation FAT organization chart
Figure 4 – Substation FAT organization chart

Go back to Content Table ↑


4.4 Technical Specification

Figure 5 – Substation technical specification

Substation project specification
Figure 5 – Substation project specification

Go back to Content Table ↑


4.5 Review QA/QC Procedures & Forms

Quality Assurance / Quality Control (QA/QC)

  1. Discuss test description, method of test and responsible party for each equipment type.
  2. Define customer inspection policy and specify if additional tests are required.

Go back to Content Table ↑


4.6 Capture Meeting Minutes

It’s important to document major discussion points, resolutions, action items and the corresponding team member responsible for those actions.

Useful Study – Technical Documentation for a Turnkey Substation

Technical Documentation for a Turnkey Substation

Go back to Content Table ↑


5. Safety Precautions During Electrical Inspection

5.1 PPE for Electrical Inspection

  • Safety Glasses: to be used when circuit bridging (jumpering)
  • Touchless AC voltage indicator: to detect the presence of AC voltage
  • Lock out device: for electrical lockout/tagout
  • Hasp: for electrical lockout/tagout
  • Personal lock & tag: for electrical lockout/tagout

5.2 General Safety Precautions and Checks

  • Do not wear conducive article of jewelry and clothing.

Figure 6 – Do not wear conducive article of jewelry and clothing

Do not wear conducive article of jewelry and clothing
Figure 6 – Do not wear conducive article of jewelry and clothing
  • Always use test equipment that is in good working order and in safe condition.
  • Always assume all conductors are “HOT” until verified to be de-energized.
  • A ground wire must be attached to all equipment under test and to all test equipment prior to energizing.
  • Get acquainted with the equipment to be tested prior to energization.
  • When using wall or floor junction boxes, the power cable should be secured to the box to prevent the cable from being unplugged.
  • Arrange power cords or other types of extension cords such that it prevents a trip hazard.
  • Always turn off test equipment and disconnect from the source before disconnecting it from the job.
  • PT and CPT primary circuit fuses MUST be removed when running secondary voltage unless the primary is energized with bus wires removed from the fuse block.
  • Power factor correction capacitors and surge arrestor should not be energized.
  • Never use alligator clips to attach high voltage test carts leads to the bus bar.
  • Define the boundaries that prohibit unauthorized personnel from entering the restricted area.

Figure 7 – Boundaries that prohibit unauthorized personnel from entering the restricted area

Restricted area
Figure 7 – Restricted area
  • Use warning lights on the test equipment to warn area personnel of presence of voltage on the equipment.

Figure 8 – Warning lights on the test equipment during the FAT

Warning lights on the test equipment during the FAT
Figure 8 – Warning lights on the test equipment during the FAT
  • Limit the use of high voltage as much as possible. Ensure that all high voltage test leads are color coded and readily identifiable. “A” phase is black, “B” phase is red and “C” phase is yellow.

Membership Upgrade Required

This content is not available in your premium membership plan. Please upgrade your plan in order to access this content. You can choose an annually based Basic, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers.

With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Limited Time Gift! – Save 10% on Pro Membership Plan with code 110VDC

Upgrade

Already a member? Log in here

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
Edvard Csanyi - Author at EEP-Electrical Engineering Portal

Edvard Csanyi

Hi, I'm an electrical engineer, programmer and founder of EEP - Electrical Engineering Portal. I worked twelve years at Schneider Electric in the position of technical support for low- and medium-voltage projects and the design of busbar trunking systems.

I'm highly specialized in the design of LV/MV switchgear and low-voltage, high-power busbar trunking (<6300A) in substations, commercial buildings and industry facilities. I'm also a professional in AutoCAD programming.

Profile: Edvard Csanyi

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

9  ×  1  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

EEP Hand-Crafted Video Courses

Check more than a hundred hand-crafted video courses and learn from experienced engineers. Lifetime access included.
Experience matters. Premium membership gives you an opportunity to study specialized technical articles, online video courses, electrical engineering guides, and papers written by experienced electrical engineers.